Hello all- I'm sorry for the long intervals between posts but between teaching, building, and getting my masters, things are falling through the cracks. :)
The plumber and electrician are in and working they both say that around the end of the week they should be finished. That brings us to inspection then insulation.
Right now, I am torn between two different systems: a closed cell-hybrid or open cell system.
Closed-Cell Open-Cell
Highest insulating "R-Value" per inch (> 6.0) Good insulation value (R = 3.5)
Low vapor permeability (low perm) Higher vapor permeability, but controlled
Air barrier Air barrier at full wall thickness
Increases wall strength
(is a WRB – "Water Resistive Barrier")
Medium density (1.75 – 2.25 lbs./ft3) Low density (0.4 – 1.2 lbs./ft3)
Absorbs sound, especially bass tones Best sound absorption in normal frequency ranges
Economical yield
In either case, I am going to get very good insulation. In the closed cell hybrid system, 2 inches of closed cell foam is sprayed to create an air/water barrier with excellent insulating value (R-value). Then fiberglass rolls (bats) are placed over the foam to increase the R-value.
The open cell system simply fills the whole wall cavity with the open cell foam. Each system has advantages and disadvantages. They are both about the same in price and R-value. I am not sure which system I will use.
Thanks for reading.
Tuesday, November 2, 2010
Tuesday, October 12, 2010
subcontractors
I have to say that up to this point I feel pretty lucky. As you all know, I have been the general contractor (GC) for this project. Usually owners hire a GC to find (or do) all the subcontracting work. The GC has a budget, which had been mutually worked out by the owner and GC, and it's up to them to keep everything together. I am learning so much, so quickly about building that frequently it makes my head spin. Luckily, I have family that has helped me in the design and budget phase, (Thanks Tom), family in the construction business (thanks Tim, Russ, Jason, Dave, Steve) that have not only helped in building this house, but have given great advice and gave me questions to ask when I knew nothing. :) I am currently looking for bids on vinyl siding-
I read that for all contract work, (not just siding) I should be looking for 3 or 4 bids to get a feel for the cost. I also surf the web to get retail pricing on materials, although I know that siding isn't JUST siding, it has a lot of extra costs, like under insulation, nails, soffits, etc... I also like to find out reasonable pricing for labor. There are many places you can get this kind of information. http://www.siding4u.com/vinyl-siding-cost-calculator.php for example was a place to get rough estimates on cost of a siding job.
So, I had a budget in place for siding, and went looking. In the past week I received four bids. All of them were from (seemingly) repatable companies.
The prices ranged from 8000.00 to 40,000.00 dollars!
Admittedly the one from Sears, (yeah I know) which was the 40k bid had bunches of incentives, which dropped the price down to 28,000- WITH an additional 750 gift card.... but really? Almost a four time spread?
I guess the bottom line is that you need to do your homework, have an idea of what a job should cost and get multipule bids. It's a jungle out there.
Thanks for reading
Sam
I read that for all contract work, (not just siding) I should be looking for 3 or 4 bids to get a feel for the cost. I also surf the web to get retail pricing on materials, although I know that siding isn't JUST siding, it has a lot of extra costs, like under insulation, nails, soffits, etc... I also like to find out reasonable pricing for labor. There are many places you can get this kind of information. http://www.siding4u.com/vinyl-siding-cost-calculator.php for example was a place to get rough estimates on cost of a siding job.
So, I had a budget in place for siding, and went looking. In the past week I received four bids. All of them were from (seemingly) repatable companies.
The prices ranged from 8000.00 to 40,000.00 dollars!
Admittedly the one from Sears, (yeah I know) which was the 40k bid had bunches of incentives, which dropped the price down to 28,000- WITH an additional 750 gift card.... but really? Almost a four time spread?
I guess the bottom line is that you need to do your homework, have an idea of what a job should cost and get multipule bids. It's a jungle out there.
Thanks for reading
Sam
Thursday, October 7, 2010
forging ahead
Things seem to finally be swinging our way- The lumber came in under budget, as did the shingles. Our decision to drastically reduce our front porch, from one that stretches the whole length of the house to the one that you can see in the pictures below, help trim some money. We also made some cuts in the fixtures. We are really trying to get back to our budget. You can see Steven White starting to shingle our roof, and the windows and doors are all in. Ben and I took some interior shots. You can really see the duct work for the geothermal system.
Thanks for reading.
Thanks for reading.
Thursday, September 23, 2010
solar documentation
We received a large packet today regarding our solar panels- We will be generating about 62% of our electricity via the panels, and here are some of the statistics from it:
Environmental Impact Analysis
25-year Carbon Dioxide Reduction 155,214 Pounds
25-year Sulfur Dioxide Reduction 658 Pounds
25-year Nitrogen Oxides Reduction 260 Pounds
Avoided Fossil and Nuclear Fuel Use:
Equivalent to planting 724 trees or avoiding 169,782 miles of driving
Environmental Impact Analysis
25-year Carbon Dioxide Reduction 155,214 Pounds
25-year Sulfur Dioxide Reduction 658 Pounds
25-year Nitrogen Oxides Reduction 260 Pounds
Avoided Fossil and Nuclear Fuel Use:
Equivalent to planting 724 trees or avoiding 169,782 miles of driving
Wednesday, September 22, 2010
Tuesday, September 21, 2010
framing almost finished
As the title suggests, the framing is almost done. Teri and I are so excited about this part of the project. It has been a real pleasure to work with Jim Engel. He constantly worked with us; giving ideas about different things we can do with our space. It's beautiful inside and out. Tim Pallas, our electrician and part-time GC, told us that from this point on, we can expect things to stay on budget, and we will know before hand about any "extras". I am still worried though because we burned thru alot more then we thought for the clearing and excavating of the property. Ah, well, who needs a kitchen anyways. :) Honestly, we are going to be breathing fumes by the time we get near the end. Landscaping, interior molding, and extras are going to have to wait I think.
I will post up some pictures of the outside soon. The porches are finished, and are absolutely stunning. We changed the front porch from one that stretches the whole length of the house to one that is a more modest 14 feet- enough to get into the house, and also to be able to put a couple of chairs or planters on. The side porch is the length of the width of the house, 24 feet. We decided to use a wood composite product for the decking. It is durable and won't need painting or staining for the life of the deck. (About 20 years.)
The second floor has some changes also. Because of the reorientation of the garage to the house we had to move where the garage stairs to the bonus room was placed. That gave us some extra space upstairs, and we used it to make a separate laundry room. The upstairs main bath is HUGE- and gives a great view of the lake. We will be able to put in (eventually) some custom linen closets and be able to actually store our towels and such. YEA!
This past week has also been very busy meeting with subcontractors. I met with a cabinet maker who took measurements of the kitchen and will be plugging in the numbers into a software program to give us a 3-d view of our cabinets. Cool.
I had a walkthrough with the geothermal guys, they are going to lay the ducts within the next two weeks, and will be drilling the well at about the same time.
The solar panel installer came to measure our roof, and get a read on the amount of sunlight we will get. He says that the monthly cost of the lease will be a bit higher than the electricity we will produce, but I'm pretty sure that I still want to do it for a few reasons:
I will post up some pictures of the outside soon. The porches are finished, and are absolutely stunning. We changed the front porch from one that stretches the whole length of the house to one that is a more modest 14 feet- enough to get into the house, and also to be able to put a couple of chairs or planters on. The side porch is the length of the width of the house, 24 feet. We decided to use a wood composite product for the decking. It is durable and won't need painting or staining for the life of the deck. (About 20 years.)
The second floor has some changes also. Because of the reorientation of the garage to the house we had to move where the garage stairs to the bonus room was placed. That gave us some extra space upstairs, and we used it to make a separate laundry room. The upstairs main bath is HUGE- and gives a great view of the lake. We will be able to put in (eventually) some custom linen closets and be able to actually store our towels and such. YEA!
This past week has also been very busy meeting with subcontractors. I met with a cabinet maker who took measurements of the kitchen and will be plugging in the numbers into a software program to give us a 3-d view of our cabinets. Cool.
I had a walkthrough with the geothermal guys, they are going to lay the ducts within the next two weeks, and will be drilling the well at about the same time.
The solar panel installer came to measure our roof, and get a read on the amount of sunlight we will get. He says that the monthly cost of the lease will be a bit higher than the electricity we will produce, but I'm pretty sure that I still want to do it for a few reasons:
- The price of electricity keeps increasing. It has double in the last decade, about 10% a year, but the lease price is guaranteed for 15 years, so right now it costs a little more per month, but if the price keeps rising, I will be locked in at the lower price, and could save a lot of money in the long run.
- At the end of the lease I will own the panels and infrastructure (panels, wires and such) which might not be great because of the advancing technology of the panels, but the panels are rated for 40years.
- It is the "green" way to go, and even if it is a few dollars more right now, I know that the energy that I am using comes from a renewable source.